Schedule Calendar Report
Read your Schedule Calendar: each lot's critical path and sub path rows, your tasks as bars coloured by task type, task and lot details on hover or tap, and search and filters to find your work.
Overview
The Schedule Calendar is a week-by-week view of every lot you have work on, from the start of last week onward. Each of your tasks is drawn as a coloured bar across the days it runs, beside the other trades' work on the same lot, so you can see what has to finish before you go out and spot two jobs landing at once. Trade partners open it from the Reports section of their Trade Partner Portal or from a link their builder sends β no sign-in needed β and builder staff can open the same report from a trade partner's page.
Watch the video
See how to read the calendar, find the work you need, and print it, in under two minutes.
Getting to the Schedule Calendar
Trade partners: in your Trade Partner Portal, click Schedule Calendar under Reports. A Schedule Calendar link from your builder opens the same report straight away.
Builder staff: open the trade partner from the Trade Partners page and click Schedule Calendar under Reports.
How to read the calendar
Lots run down the page. Each lot starts with its name in the Lot column, and a solid line separates one lot from the next. Lots are in order of when your work on them starts, earliest first.
The critical path is on top. A lot's first row is its critical path β the work the rest of the build waits on. Its sub path rows sit underneath, below a dashed line.
Weeks run across. Each week is headed by its Monday's date, such as Oct 12. Under it, each work day shows a weekday letter (M, Tu, W, Th, F) above the date. Weekends aren't shown.
Each task is a bar from its start date to its due date. Its short abbreviation, such as RP, is printed once, on the day the bar starts.
Your tasks are coloured, one colour per task type. Other trades' tasks are grey. The line under the title shows one colour square for each of your task types on the calendar right now, beside the grey Other trades chip.
Finished tasks are outlined. With Show completed on, a finished task is drawn as an outline in its usual colour, empty inside. Other trades' finished tasks are outlined in grey.
Today is the column marked TODAY. A holiday's date is crossed out.
π‘ Tip: The grey tasks are the work happening around yours on the same lot. They're there on purpose, so you can see what has to finish before you go out.
How to see the details of a task
Hover over a task's bar. On a phone or tablet, tap it.
A card shows the task's full name and abbreviation, whether it's on the Critical path or Sub path, and its status: Not started, In progress, Overdue or Completed.
Below that you'll see who the task is assigned to and their trade, its start and due dates, and how many working days it runs.
A task in progress shows how far along it is, such as Day 3 of 5. An overdue task shows how many working days it is past due, and a finished task shows the date it was completed.
How to see a lot's address and contacts
Click the lot's name in the Lot column.
A window opens with the lot's Location, its Construction manager with their phone number and email, its Community, and its Permit number with the date it was issued. Tap the phone number to call or the email to write.
Click Lot files to open the lot's files in a new tab. The button is there when your builder has linked the lot's files.
Press Escape or click the close button when you're done.
How to find the work you need
The controls above the calendar change what's shown on your screen. They never change the schedule itself.
Search tasks β type part of a task's name or abbreviation. Lots without a match are hidden, and on the lots that remain, tasks that don't match fade out.
Communities β tick one or more communities to show only their lots.
Lots β tick one or more lots to show only those. Type in Search lots to find a lot in a long list.
Tasks β tick one or more of your task types, such as TO - Top Out, to show only the lots where you have that kind of work. Only the types you tick keep their colour; your other task types turn grey. Type in Search task types to find one in a long list.
Show completed β turn it on to see finished work from the start of last week onward. It starts off every time you open the report.
Expand all β show every sub path row on every lot. To open just one lot, click the arrow next to its name.
How to print the calendar
Set the calendar up the way you want it on paper: search, filters, Show completed and any lots you've expanded.
Click the round print button in the bottom-right corner.
The printout shows the lots and rows on your screen right now. The controls and the print button are left off the page.
Extra lot details you may see
Your builder can add up to six extra columns of lot detail to this report. They sit between the lot name and the first week of the calendar. Whether you see them β and which of them you see β is your builder's choice, so your report may show all six, a few, or none at all.
The same details also appear in the window that opens when you click a lot's name.
You get every column your builder added at any screen size. On a wide screen they stay put beside the lot name while you scroll through the weeks. On a narrow window or a phone they scroll sideways with the calendar instead, so swipe across to reach them β the same swipe that takes you to later weeks. The lot name stays put either way, so you always know which row you're reading.
These columns are read-only detail about the lot, like the rest of the report β no sign-in, and nothing for you to turn on, hide, or reorder. If you administer a builder account yourself, Trade Partner Schedule Calendar Columns covers how these are chosen.
βΉοΈ Note: The red, amber and green on Target Close and Target Quarter are about the lot's closing dates. They have nothing to do with the colours on your task bars, which only tell you which of your task types you're looking at.
Frequently Asked Questions
What do the colours on my Schedule Calendar mean?
What do the colours on my Schedule Calendar mean?
Your own tasks are coloured, with one colour for each of your task types. If you have Rough Plumbing, Top Out and Trim Out on the report, you'll see three colours, and every Rough Plumbing bar is the same colour on every lot and in every week. Grey bars belong to other trades and are there for context.
If you've ticked task types in the Tasks filter, only those types keep their colour, and your other task types are grey until you clear it.
A bar drawn as an outline, empty inside, is a finished task, shown only while Show completed is on. A red abbreviation means the task is overdue. To check which job a colour stands for, hover over the bar, or tap it on a phone or tablet. The card that opens is tinted in that task's colour.
The colours only tell you which of your task types you're looking at. They don't mean urgent, late or approved.
Why does one lot have more than one row on the Schedule Calendar?
Why does one lot have more than one row on the Schedule Calendar?
Each row only ever holds one task per day. A lot's first row is its critical path β the work the rest of the build waits on β and its sub path work sits on the rows below it. When two tasks overlap on the same days, they go on separate rows so you can see both. A lot with a lot of overlapping work can take several rows.
Why can't I see every task on a lot?
Why can't I see every task on a lot?
Each lot opens folded up. You see its critical path, plus the sub path rows that hold your own tasks. Sub path rows with only other trades' work are tucked away.
To see them, click the arrow next to the lot's name, or click Expand all above the calendar to open every lot at once. Click Collapse all to fold them back up. A lot with nothing more to show has no arrow.
If you're searching, a folded lot also shows any sub path row with a task that matches your search. Finished tasks only show while Show completed is on.
What changed on the Schedule Calendar?
What changed on the Schedule Calendar?
The calendar was rebuilt to be easier to read. Your task types still each get their own colour, and other trades' work is still shown. What's different:
Each task is one bar from its start date to its due date, with its abbreviation printed once where it starts. There are no more X marks on the days a task carries on.
Tasks that overlap now go on separate rows. A day is never split into two stacked colours, and there's no + for a busy day any more.
The critical path is always the lot's first row, with sub path rows underneath.
The colour squares under the title now match your task types on the calendar, one square per type, instead of a small sample.
Hovering or tapping a task shows a card about that one task, including who it's assigned to and how many working days it runs.
Clicking a lot's name shows its address, construction manager, community, permit and files.
You can search tasks, pick communities, lots and task types, and turn on Show completed to see finished work.
Why don't I see my finished tasks on the Schedule Calendar?
Why don't I see my finished tasks on the Schedule Calendar?
Show completed is off every time you open the report, so the calendar starts with the work still to do. Turn it on above the calendar to see finished tasks, drawn as outlines in their usual colour, empty inside. A finished task that runs over several days is one continuous outline, and other trades' finished tasks are outlined in grey. It covers tasks due from the start of last week onward, whenever they were finished; a task due before that isn't on the report.
Why does the Schedule Calendar say "No lots match these filters."?
Why does the Schedule Calendar say "No lots match these filters."?
Your search, or the communities, lots or task types you've picked, hide every lot on the report. Click Clear filters to empty the search and the community, lot and task type choices and see everything again. Show completed stays as you set it.
Why does the Schedule Calendar say "No open tasks to show."?
Why does the Schedule Calendar say "No open tasks to show."?
The only work left to show is finished work, and Show completed is off. Turn on Show completed to see it. If you've searched or picked communities, lots or task types, Clear filters is there too.
Why is a task's abbreviation red on the Schedule Calendar?
Why is a task's abbreviation red on the Schedule Calendar?
The task is overdue: it isn't marked complete and its due date has passed. A task is never overdue on its own due date. Hover over the bar, or tap it on a phone or tablet, to see how many working days it's past due. If the work is actually done, ask your builder to mark it complete.
Will the same job always be the same colour?
Will the same job always be the same colour?
On the same link, yes. Reload it as often as you like, search, pick communities, lots or task types, or turn Show completed on and off β the colours stay put. Ticking task types in the Tasks filter turns your other types grey, but each type you tick keeps the same colour it always has. Colours can differ between two different links, though. A link filtered to one trade may give a job a different colour than your full calendar does, because each link works out its colours from the tasks on that report. Hover over a bar on the link you're looking at to check.
Two of my jobs have the same colour. Is that a mistake?
Two of my jobs have the same colour. Is that a mistake?
No. There are ten colours available. If you have more than ten different task types on the report, colours start repeating. We'd rather two jobs share a colour than leave one of your tasks without one. Hover over the bar to see exactly which job it is.
Some tasks on my Schedule Calendar are grey. Why?
Some tasks on my Schedule Calendar are grey. Why?
Grey tasks belong to a different trade partner. They're shown so you can see the work happening around yours on the same lot. Hover over one to see whose it is. If you opened a link filtered to one of your trades, your work on your other trades shows in grey too.
If you've ticked task types in the Tasks filter, your own tasks of the types you didn't tick are grey as well. Clear the Tasks selection to bring their colours back.
Why don't I see the Communities, Lots or Tasks filter?
Why don't I see the Communities, Lots or Tasks filter?
Each one only appears when there's something to choose between. Communities shows when your lots on the report are in two or more communities, Lots shows when there are two or more lots, and Tasks shows when you have two or more task types on the report. Turning on Show completed can bring in more lots, communities and task types, because it adds your finished work.
What happens to my other tasks when I pick a task type in the Tasks filter?
What happens to my other tasks when I pick a task type in the Tasks filter?
They stay on the calendar, in grey. When you tick one or more task types, the Schedule Calendar shows only the lots where you have a task of a ticked type, and only the ticked types keep their colour. Your other task types turn grey, like other trades' tasks, on the bars and on the card you see when you hover over or tap them. Everything is still there, so you can see the work around yours.
A type you tick keeps the same colour it always has. Untick everything, or click Clear in the list, and every type gets its colour back. To fade out everything except one job, type its name or abbreviation in Search tasks instead.
Only your own task types are listed in the Tasks filter. Each type is listed as its abbreviation, a dash and its name, such as DS - Drywall sand. A type with no abbreviation is listed by its name alone.
What are the colour squares under the Schedule Calendar title?
What are the colour squares under the Schedule Calendar title?
They're your colour key. There's one square for each of your task types on the calendar right now, in the same colour as that type's bars, next to a grey Other trades chip for everyone else's work. When you search, filter or turn Show completed on or off, the squares change to match what's on screen. If you've ticked task types in the Tasks filter, only the ticked types that are on screen get a square.
The squares aren't labelled. To see which job a colour stands for, hover over one of its bars, or tap it on a phone or tablet. If none of your tasks are showing, only the Other trades chip is there.
Can I sort the lots on the Schedule Calendar?
Can I sort the lots on the Schedule Calendar?
Yes. Click the Lot heading to sort lots by name, A to Z. Click it again for Z to A, and once more to go back to the usual order, where the lot your work starts on soonest is first. Any extra lot detail column your builder has added sorts the same way. A lot's rows always stay together.
Does the Schedule Calendar remember my search and filters?
Does the Schedule Calendar remember my search and filters?
No. Every time you open or reload the report, it starts fresh: no search, every community, lot and task type shown, Show completed off and every lot folded up. Nothing you change is saved or shared with anyone else who opens the link.
What does the line down one day of a lot mean?
What does the line down one day of a lot mean?
A line down the right-hand edge of one day marks the lot's target close date β the date your builder is aiming to close the lot. You only see it when your builder has added the Target Close column to your report.
What are the extra columns between the lot name and the calendar?
What are the extra columns between the lot name and the calendar?
They're lot details your builder has chosen to add to the Schedule Calendar report. There are up to six: Actual Start (the earliest date any scheduled task on the lot can start), Projected Close (the latest due date across the lot's scheduled tasks), Target Close (the date your builder is aiming to close the lot), Target Quarter (the quarter they're aiming to close in), Build Days (buildable days from the actual start to the projected close, with hold time taken out) and Project Manager (the project manager's last name). They're read-only detail about the lot β the report still needs no sign-in and still can't be edited.
Why don't I see the Actual Start or Target Close columns on my Schedule Calendar?
Why don't I see the Actual Start or Target Close columns on my Schedule Calendar?
Your builder hasn't added them. Builders choose which lot details to show and which trade partners see them, so another partner's report can have columns yours doesn't. There's no setting on your side to switch them on β if you need one of them, ask your builder. If you administer a builder account yourself, Trade Partner Schedule Calendar Columns explains how to add them.
On a phone or a narrow window, check that the column isn't simply off to the right before you ask. The extra detail columns scroll sideways with the calendar on a narrow screen, so scroll across from the lot name and they'll come into view.
Why do I have to scroll sideways to see the extra lot details on my phone?
Why do I have to scroll sideways to see the extra lot details on my phone?
There isn't room to hold them still. On a wide screen the extra lot detail columns β Actual Start, Projected Close, Target Close, Target Quarter, Build Days and Project Manager β stay fixed beside the lot name while the weeks scroll past them. On a phone that block would leave almost no room for the calendar itself, so the details scroll along with the weeks instead.
Nothing is missing. Every column your builder added is still on the report β scroll sideways from the lot name to reach them, the same way you scroll to reach later weeks. The lot name stays fixed at any size, so you don't lose track of which row you're on. You may find a wide table easier to read with your phone turned sideways, but you don't need to turn it to see anything.
Why is a Target Close date red or amber on my Schedule Calendar?
Why is a Target Close date red or amber on my Schedule Calendar?
Red means the lot's projected close has already slipped past the date your builder is targeting for closing. Amber means it hasn't slipped yet, but it's within about 15 working days of that target. Any other lot shows in the normal text colour. This colouring is only about closing dates β it isn't related to the colours on your task bars, and it doesn't say anything about your own tasks being late.
What does the Target Quarter column mean?
What does the Target Quarter column mean?
It's the quarter your builder is aiming to close that lot in, written like Y26 Q3. The text turns red when the lot is now projected to close later than that quarter, and green when it's projected to close earlier. On a computer, hover over the value and it shows the quarter the lot is currently projected to close in, so you can see what it's being compared against. On a phone, tap the lot name instead: the lot details window shows the projected quarter under the Target Quarter value, as Projected: followed by the quarter. It's read-only, like the rest of the report.
Why is the Build Days column blank for one of my lots?
Why is the Build Days column blank for one of my lots?
That lot is on an open hold. Build Days counts the buildable days from the lot's actual start to its projected close with hold time taken out, and while a hold is still open there's no way to know how long the build will run β so the cell stays blank instead of showing a number that's about to change. It fills back in once the hold ends.
Can I turn the extra lot detail columns on or off, or change their order?
Can I turn the extra lot detail columns on or off, or change their order?
No. The extra columns on the Schedule Calendar report β Actual Start, Projected Close, Target Close, Target Quarter, Build Days and Project Manager β are chosen by your builder, and their order is fixed. The whole report is view-only, so there's no menu to show, hide, or move a column. You can click a column's heading to sort the lots by it, but that only changes the order of the lots. If you'd like one added or removed, ask your builder.
Your screen size doesn't change what's on the report either. It only changes whether the columns stay fixed beside the lot name or scroll sideways with the calendar.
Does this report follow my device's dark appearance?
Does this report follow my device's dark appearance?
No. This report always shows on a light background, whether or not your phone or computer is set to a dark appearance. That keeps the colours looking the same for everyone and the same on screen as on paper, so a colour you agree on with your builder means the same thing to both of you.
A date on the calendar is wrong. Can I change it?
A date on the calendar is wrong. Can I change it?
The report is view-only. Every date on it comes from your builder's schedule, so contact your builder and they can correct it. Click the lot's name to find its construction manager's phone number and email.
Why does the Schedule Calendar say "No tasks to show"?
Why does the Schedule Calendar say "No tasks to show"?
That means none of your scheduled work is due from the start of last week onward, finished or not, so there's nothing to draw. It isn't an error, and the report will fill back in as your builder schedules work.
Was this helpful?
More in Trade Partners
Getting StartedTrade Partner PortalDaily ReportsOn Site ListStill need help? Ask the team