Trade Grade Leaderboard

See how your trade partners stack up on schedule performance over the past 30, 60, and 90 days.

Overview

The Trade Grade Leaderboard ranks your trade partners by how closely their completed tasks finished on schedule over the last 30, 60, and 90 days. Managers use it to recognize the partners who consistently hit their dates, spot the ones whose work tends to slip, and open a partner's page for the detail behind the grade.

How rankings are determined

Each grade is based on drift: the number of working days between a task's due date and the date it was actually completed. Finishing a task early produces negative drift, finishing on the due date is zero, and finishing late produces positive drift. For every trade partner, the leaderboard averages the drift of all tasks they completed inside each rolling window — the last 30 days, the last 60 days, and the last 90 days — to produce three separate grades.

Lower drift is better, so the displayed grade is the inverted average (a partner who averaged 2 working days late shows as -2.0; a partner who averaged 1 day early shows as 1.0). The progress bar next to each grade uses the raw drift to color-code performance: up to 4 working days late shows green, more than 4 and up to 12 days late shows yellow, and anything beyond 12 days late shows red. A red warning triangle appears once average drift reaches 20 working days late, flagging partners whose schedule slip has crossed into a problem range.

What you'll see

On desktop, the page shows a sortable table with five columns: Name, Trade, 30 Day Grade, 60 Day Grade, and 90 Day Grade. Click any column header to sort by it; rows with no data for a given grade column are always anchored at the bottom regardless of sort direction. By default the table sorts by the 30-day grade. A partner with no trades assigned shows No Trade in the Trade column. Trade partners with no completed tasks across all three windows are hidden from the table, and a footer note tells you how many are hidden.

On mobile, the leaderboard collapses to a single list with a segmented control at the top to pick the 30-, 60-, or 90-day window and a button to flip the sort direction. Only partners with data for the selected window appear; the rest are counted in the footer note.

Clicking or tapping any row opens that trade partner's page, where you can drill into the underlying tasks driving the grade.

Frequently Asked Questions

For each window (30, 60, or 90 days), TPTM takes every task the partner completed in that window and measures its drift — the working days between the task's due date and the date it was marked complete, skipping weekends and your builder's holidays. The grade is the average drift with the sign flipped, so a partner who averages 2 days late shows -2.0 and a partner who averages 1 day early shows 1.0. Higher is better.

Two things matter most. First, update task completion dates promptly: drift is calculated from the date a task was marked complete, so entering an on-time finish days later pulls the grade down unfairly. Second, set realistic due dates up front: a pattern of small slips across many tasks moves a grade more than one or two large misses, so accurate scheduling pays off across the whole window.

Review the 30-day grade weekly — it reacts fastest to recent changes, so it's the best way to confirm that a process change is actually moving the needle before judging the 60- and 90-day trends. Start with any partner showing a red warning triangle: their average drift has reached 20 working days late.

Click or tap the partner's row to open their trade partner page. For a full breakdown of one partner's completed tasks by community and task type over a date range, use the Trade Partner Performance Report.

Partners with no completed tasks in any of the three windows have no grade to show, so they're hidden from the table and counted in the footer note ("N trade partners hidden due to no grade data"). Archived trade partners never appear. On mobile, a partner is also hidden while the selected window has no data for them — switch to the 60- or 90-day window and they may reappear.

The partner completed no tasks inside that particular window. A blank grade never sorts as the best or worst value — rows without data for the sorted column always sit at the bottom, whichever direction you sort.

The bar next to each grade is colored from the partner's average drift: green when they average 4 working days late or better (including early), yellow from more than 4 up to 12 days late, and red beyond 12 days late. A warning triangle appears once average drift reaches 20 working days late. Early completions never turn a bar red or show the triangle.

The trade partner has no trades assigned to their record. Their grades are still calculated normally; the label simply fills the Trade column instead of leaving it blank.

No. The leaderboard always uses the fixed 30-, 60-, and 90-day windows counted back from today. For a custom date range on a single partner, use the Trade Partner Performance Report.

Grades are recalculated from your live task data every time the page loads — there is no overnight refresh to wait for. Marking a task complete shows up in the grade the next time you open or reload the leaderboard.

An error message appears in place of the table with a Try again button. Click it to reload the data. If the leaderboard stays empty and you expect to see partners, your role may be missing permission to view trade partners, trades, or tasks — ask your administrator.