Lot Highlighting in the Schedule Table
Highlight the lot rows you are watching on the Overall timeline so they stand out in the grid, and clear them when you are done.
Overview
Lot highlighting tints a whole lot row on the Overall timeline so the lots you care about stand out from the rest. Use it to keep an eye on the lots you are actively working, to walk a meeting through a handful of lots, or to see where the lots you just batch-scheduled landed. Anyone who uses the timeline can highlight lots, and the highlights are yours alone — they do not change the schedule or what other people see.
How to highlight a lot
Open Schedule in the navigation and click Overall timeline.
Right-click any cell in the lot's row.
Choose Highlight lot. The whole row — lot columns and day cells — turns blue.
To remove one highlight, right-click the row again and choose Remove lot highlight.
How to clear all highlights
Open the Settings tab in the sidebar on the right of the timeline.
Under Lot Highlighting, Lots shows how many lots are highlighted.
Click Clear Lot Highlights.
Frequently Asked Questions
What does a highlighted lot look like?
What does a highlighted lot look like?
The entire row is tinted blue across every column. The grid alternates two shades of blue from row to row so neighbouring highlighted lots stay easy to tell apart. In dark mode the tint is a darker shade of the same colour.
Why is one cell in a highlighted row a different colour?
Why is one cell in a highlighted row a different colour?
Other colours take priority over the lot highlight in a single day cell: a task that matches a text or trade partner highlight from the Highlighting tab, the day you picked in Highlight day, and days the lot was on hold all paint over the lot highlight. A task that starts or ends on a weekend paints the cell red on top of everything. The lot highlight itself paints over holiday shading.
Do my highlights stay when I come back later?
Do my highlights stay when I come back later?
Yes. Highlights are saved in your browser for this company, so they survive a refresh and are still there the next time you open the timeline on the same device. They are not shared with other people or with your other devices. Clicking Reset on the timeline clears them along with the other schedule settings.
Why are lots highlighted that I never picked?
Why are lots highlighted that I never picked?
After you run Batch schedule, the timeline opens with the lots you just scheduled highlighted so you can see where they landed. Clear them with Clear Lot Highlights in the Settings tab whenever you like.
Does highlighting hide the other lots?
Does highlighting hide the other lots?
No. Highlighting only changes colours — every lot stays in the grid. To show only certain lots, use the Filters tab in the sidebar instead.
Can I highlight more than one lot?
Can I highlight more than one lot?
Yes. Right-click and choose Highlight lot on as many rows as you like; the Lots count in the Settings tab keeps track of how many are highlighted.
My highlights are not showing — what should I check?
My highlights are not showing — what should I check?
Right-click the row and make sure the menu offers Remove lot highlight — if it still says Highlight lot, the lot is not highlighted. Check whether someone clicked Clear Lot Highlights or Reset on this device, then try refreshing the page. Highlights made on another computer or phone will not appear here.