Set up your company's holidays once — recurring rules, ready-made presets or one-off dates — so schedules skip the days nobody is working, and move work that already sits on a holiday.

Overview

Settings → Holidays is your company's list of the days nobody is working. Schedules never place work on those days and timeliness counts skip them, so keeping the list right keeps every lot's dates honest. Set up recurring holidays once — from ready-made presets or your own rule — add any one-off dates, and TPTM fills in every date from today through the next two years for you. If a holiday lands on work that was already scheduled, the same page tells you and moves those schedules off it in one step, along with any lots that depend on them.

Watch the video

See how to set up your holidays and move work that lands on one, in three and a half minutes.

Getting to the Holidays page

  1. Open Settings from the sidebar.

  2. Click Holidays.

Below the Select presets and Add holiday buttons is one list of your holidays, with a switch above it: Upcoming (shown when the page opens) and Past. A recurring holiday — one that comes back every year — is marked with a small repeat icon after its name.

How to choose the US federal and common holidays

  1. Click Select presets. The button shows how many of the ready-made holidays you already have, for example Select presets (7/15).

  2. Check each holiday you want and uncheck any you don't. The holidays are listed in two groups, US federal holidays and Other common business holidays, and the ones you already have are checked.

  3. Click Save.

You see Presets updated. Each holiday you checked appears in the list as a recurring holiday with a Preset tag and its Next date, and TPTM fills in its dates from today through the next two years. Each holiday you unchecked leaves the list.

How to add your own recurring holiday

  1. Click Add holiday.

  2. At the top of the Create Holiday panel, choose Recurring.

  3. Enter a Name.

  4. Choose a Type:

    • Fixed date — the same date every year. Pick the Month and Day, for example July 4.

    • Weekday of a month — pick the Month, Which (1st, 2nd, 3rd, 4th or Last) and Weekday, for example the 4th Thursday of November, or the Last Monday of May.

    • Relative to Easter — the date is counted from Easter Sunday using the offset in the next step. Good Friday is an offset of −2; Easter Monday is +1.

  5. Set Days offset only if the holiday sits a few days away from the date you described. The Day after Thanksgiving is the 4th Thursday of November with an offset of +1. Leave it at 0 for most holidays.

  6. Under If it falls on a weekend, choose what happens in a year the holiday lands on a Saturday or Sunday.

  7. Turn on Also take the bridge day if you also want the Friday after a Thursday holiday, or the Monday before a Tuesday one, off. It is off unless you turn it on.

  8. Check Next dates. It shows the next three dates this rule gives on its own and updates as you edit, so you can confirm the rule does what you meant before saving. As the note under it says, dates may shift if they land on another holiday.

  9. Click Save.

The holiday appears in the list with its Next date, and TPTM fills in its dates from today through the next two years.

How to add a one-off holiday

Use this for a date that won't repeat — a company event, or a day off this year only.

  1. Click Add holiday. The Create Holiday panel opens with One-off already chosen at the top.

  2. Enter a Name and pick the Date. Days before today are greyed out: you can pick today or any later day.

  3. Click Save.

The holiday appears under Upcoming with its Date. Click it any time to edit or delete it.

How to change or remove a recurring holiday

  1. Click the holiday's row in the list. Recurring holidays have a repeat icon after their name.

  2. Click Edit, change what you need, and click Save. To remove the holiday, click Delete and confirm.

Editing a rule rewrites its upcoming dates; deleting it removes them and takes it off Upcoming. Dates that have already passed stay as they were under Past; any the rule no longer covers become one-off holidays there. Because all your recurring holidays are worked out together, changing or deleting one rule can also move another rule's upcoming date.

What the page shows

The page shows one list of your holidays. Use the switch above it to choose what the list shows:

  • Upcoming (shown when the page opens) — each recurring holiday once, at its next date, plus each one-off holiday dated today or later. The soonest is at the top. A recurring holiday with no upcoming date comes last.

  • Past — every holiday that has already happened, one row per date, most recent first. This includes each past date a recurring holiday fell on, as well as past one-off holidays.

Under Upcoming, a recurring holiday's row shows:

  • The holiday's name with a small repeat icon right after it, and the rule in plain words underneath, such as "4th Thursday of November", "July 4", "Day after the 4th Thursday of November" or "2 days before Easter".

  • A weekend tag, only when the rule doesn't use the usual nearest-weekday choice: Keep, Following Monday or Preceding Friday. A rule with no weekend tag moves a Saturday holiday to the Friday before and a Sunday holiday to the Monday after.

  • A Bridge day tag, only when the rule takes the bridge day.

  • A Preset tag when the rule was added from a preset.

  • On the right, under Next date, the next day the holiday is actually taken, tagged observed when it was moved off a weekend or off another holiday, bridge when it is a bridge day, or not observed when it stays on a Saturday or Sunday because the rule is set to Keep on the weekend.

Under Past, a recurring holiday's date shows the holiday's name, its repeat icon and its rule in plain words, with the day it fell on under Date, tagged observed, bridge or not observed when it was one. Past rows have no other tags.

A one-off holiday's row, under either option, shows just its name and, on the right, under Date, the day it falls on.

Click a recurring holiday — under either option — to see its details: the rule in plain words, its weekend choice, Bridge day (Yes or No) and its Next dates — the next three days it is actually taken, each tagged observed, bridge or not observed when it is one. Click a one-off holiday to see, edit or delete it.

How to move work that is scheduled on a holiday

When a holiday is added after a lot's schedule was built, that lot can have work sitting on the holiday. A yellow banner at the top of the page then shows a small clock icon followed by N lots have work scheduled on a holiday. A task counts when a weekday holiday falls between its start and due dates and leaves it without enough working days to finish, or when its start date or due date is itself a weekday holiday. A task that has a spare day around a holiday inside its dates keeps its dates and is not counted. A task whose dates were already shorter than its length before the holiday — set that way by hand — isn't counted for a holiday between its dates while it still has a working day; it is only counted if the holiday is its start or due day, or leaves it no working day at all.

  1. Click Review and move.

  2. Read the preview. The summary line says how many schedules will move, how many projected close dates change, how many of those land in a different quarter, and by how many working days. Below it, each row shows the Lot, its Community, its Current close, its New close and Shift (days), how many working days it moves in all, such as +2, or 0 when only a task's start or due comes off a holiday. A close that moves into the next calendar quarter is tagged next quarter; one that moves back into the previous quarter is tagged previous quarter.

  3. Check the lots that depend on a moving lot. They move too, so they are listed as well, each with a grey line under its name such as Follows Lot 12 naming the lot that pushed it furthest — usually the one directly before it. When there are any, the summary line says how many, for example "5 schedules (2 follow lots they depend on)".

  4. Click Move N schedules. Or click Cancel to leave everything exactly as it is.

TPTM works through each schedule in order. Any task a holiday squeezed gets back its full number of working days, skipping weekends and holidays, and the work after it moves out by the same number of working days. Lots that depend on it move with it in the same step, so the lots stay in step. A task that only starts or ends on a weekday holiday keeps its working days: its start moves to the next working day, its due moves back to the last working day before the holiday, and nothing after it moves. Each moved lot's Lot Activity timeline gets a note explaining the change, for example "Schedule moved 1 working day to keep work off Juneteenth (Jun 19, 2026)." A lot that moved to keep up with another lot names that lot instead, for example "Schedule moved 1 working day to follow Lot 12 (Oak Ridge), which moved off Thanksgiving (Nov 26, 2026)." A lot whose tasks only came off a holiday at their start or end reads, for example, "Schedule adjusted to keep work off Thanksgiving (Nov 26, 2026)." Once no task is squeezed by a holiday and none starts or ends on a weekday holiday, the banner disappears.

Frequently Asked Questions

Not for recurring holidays. A rule writes its dates from today through the next two years, and once a month TPTM extends every rule so your holidays always reach two years ahead. Only one-off holidays are entered by hand, and those are for dates that don't repeat.

Each recurring holiday has its own weekend choice, set under If it falls on a weekend when you add or edit it. Holidays added from Select presets start with Observe on the nearest weekday, and you can change that afterwards. The choices are:

  • Observe on the nearest weekday (the default) — a Saturday holiday is taken on the Friday before, a Sunday holiday on the Monday after. This is the federal government's rule. Independence Day 2026 is a Saturday, so it is observed on Friday, July 3, 2026.

  • Keep on the weekend — the date stays on the Saturday or Sunday. Nobody works weekends anyway, so no working day is taken off and schedules are not affected that year. Independence Day 2027 is a Sunday, so it shows as Sun, Jul 4, 2027 with a not observed tag.

  • Observe on the following Monday or Observe on the preceding Friday — always move to that side, whichever weekend day it is.

A date that was moved shows an observed tag — beside the holiday's Next date in the list, on its row under Past, and in the rule's Next dates when you open it. Only the observed date is shown — the original weekend date is not. A date kept on the weekend shows a not observed tag in the same places, so you can see that no weekday was given off. A kept date that falls on a weekday has no tag. In the list, only a recurring holiday with a choice other than the nearest weekday shows a weekend tag; click any recurring holiday to see its weekend choice.

A bridge day is an extra day off that joins a holiday to the weekend, so nobody works a single day in between. Turn on Also take the bridge day in a rule and TPTM also takes the Friday whenever that holiday falls on a Thursday, and the Monday whenever it falls on a Tuesday. Thanksgiving is always a Thursday, so a Thanksgiving rule with the bridge day on gives you Thursday and Friday off every year.

The bridge is decided from the day the holiday is actually taken, so a holiday that was moved off a weekend onto a Friday or Monday never adds a bridge. A bridge day is also skipped when that day is already a holiday, including a one-off holiday — if you also have Christmas Day, a Christmas Eve rule with the bridge day on adds nothing in 2026, because the Friday after it is already Christmas Day. Presets are added with the bridge day off; open the rule and click Edit to turn it on. A bridge day shows a bridge tag in the rule's Next dates, and beside its Next date in the list when the bridge day is the next one.

Because Christmas Day needed its day. When two of your recurring holidays would be taken on the same weekday, one keeps that day and the other moves to the nearest free weekday on its own side of it — before it if it comes earlier in the calendar, after it if it comes later — so you never lose a day off. A federal holiday always keeps its day; otherwise the holiday that comes later in the calendar keeps it. The moved date skips weekends, other holidays and your one-off holidays, and shows an observed tag.

In 2027 Christmas Day is a Saturday, so it is observed on Friday, December 24. Christmas Eve moves to Thursday, December 23. In 2028 Christmas Eve is a Sunday and would be observed on Monday, December 25 — Christmas Day itself — so Christmas Eve moves back to Friday, December 22. New Year's Eve works the same way against New Year's Day: it moves to Thursday, December 30, 2027 and Friday, December 29, 2028. If you have a one-off holiday such as a company party on Thursday, December 23, 2027, Christmas Eve moves to Wednesday, December 22 instead, and the party keeps its name.

A holiday that comes later moves forward instead. A rule you made for July 5 moves to Tuesday, July 6, 2027, because Independence Day falls on Sunday, July 4 that year and is observed on Monday, July 5.

No. A holiday added from the US federal presets always keeps its usual day, even next to a holiday you made yourself. If another holiday lands on the same day, that other holiday is the one that moves. A federal holiday you typed in yourself as a recurring holiday with Add holiday follows the normal order instead, so add federal holidays from Select presets.

All your recurring holidays are worked out together, so two of them never take the same day. Adding, editing or deleting one rule re-works every rule's upcoming dates. For example, adding Christmas Day moves Christmas Eve 2027 to Thursday, December 23, and deleting Christmas Day again gives Christmas Eve back Friday, December 24. Dates that have already passed never move.

No. Two rules that fall on the very same date — say a Christmas Day preset and a Christmas rule you made yourself — are the same holiday twice, so they give one day off. The rule you added first keeps the date. Delete the one you don't need to keep the list tidy.

While you create or edit a rule, Next dates shows that rule on its own, before your other holidays are taken into account — that is what the note "Dates may shift if they land on another holiday" means. Once you save, the holiday's Next date in the list and the Next dates in the rule's details show the days the holiday is actually taken. They differ in two cases. The rule's holiday lands on the same day as another of your holidays and has to move, as Christmas Eve does next to Christmas Day. Or the rule takes the bridge day and another holiday — a recurring one or a one-off — already holds that day, so no bridge day is added, because that day is already off. For example, a Christmas Eve rule with the bridge day on shows Friday, December 25, 2026 as a bridge day while you edit it, but Christmas Day already holds that Friday, so the saved rule has no bridge day that year.

Under Upcoming, the list shows a recurring holiday once, with its Next date, rather than one row for every year. For the dates ahead, click the holiday to open it: Next dates lists the next three days it is actually taken, each tagged observed, bridge or not observed when it is one. For dates already behind you, switch the list to Past: each past date the holiday fell on has its own row there, with the same tags.

No. A recurring holiday's dates all come from its rule, and a rule has no one-year exceptions. Changing the rule — its weekend choice, bridge day or offset — changes every upcoming year, not just one.

Adding a one-off holiday doesn't replace the rule's date for that year. The rule still gives its own date, so you get both days off and schedules skip both. Only add a one-off if you want that extra day.

If one year has to fall on a different day instead, the only way is to delete the rule and add each year's date yourself as a one-off holiday. Deleting the rule removes all of its upcoming dates, not just that year's; its past dates stay under Past as one-off holidays. One-off holidays can be edited or deleted directly: click the holiday in the list.

Dates that have already passed are history, and timeliness was counted against them, so they never move. Editing a rule replaces only its upcoming dates. A past date the edited rule would still give stays with the rule and takes its new name. A past date it would no longer give becomes a one-off holiday under its old name: it stays under Past without the repeat icon, and you can edit or delete it yourself. Deleting a rule removes its upcoming dates, and each of its past dates stays under Past as a one-off holiday.

TPTM only adds holiday dates from today forward. A date that has already passed was worked, and adding it now would change task statuses and timeliness that were already counted. For example, an Independence Day rule added in October starts with next year's date, so that is its Next date in the list. Dates still ahead this year — Thanksgiving, say — are added as usual.

No. When a rule's holiday falls on a date that already has a one-off holiday on it, the rule takes that holiday over instead of adding a second one. The one-off row leaves the list, because the recurring holiday's row now stands for it, and the date is managed through the rule from then on. This only happens on the holiday's own day, or the weekday it is observed on when it falls on a weekend. A holiday that had to move out of another holiday's way, or a bridge day, never takes over a one-off: it skips that day, and the one-off keeps its name.

A checked preset is one your company already has. The window always shows your current presets, so you change them by checking and unchecking, then clicking Save. Checking a preset you already have never adds it twice. A preset holiday you have edited since adding it — renamed, or with a different weekend choice, offset or bridge day — still counts as that preset, so it stays checked.

When you click Save, that holiday is removed just as if you had deleted it: its upcoming dates are removed, and the dates that have already passed stay under Past as one-off holidays. This includes any changes you made to that holiday after adding it. You can check the preset again any time to add it back. Removing a preset needs the Holiday: Delete permission.

Every preset uses the federal government's rule: a holiday on a Saturday is taken on the Friday before, and one on a Sunday is taken on the Monday after. Presets are added with the bridge day off. There is no weekend choice in the Select presets window. To change either setting for one holiday, click it in the list, click Edit, and change If it falls on a weekend or Also take the bridge day.

Save only becomes available once you have changed something. If the checked presets are exactly the ones you already have — when the window opens, or after you check and uncheck back to where you started — there is nothing to save. Check or uncheck a preset and Save turns on.

A holiday can't be set in the past. In the Date picker, days before today are greyed out; today and any later day can be picked. This applies both when you add a one-off holiday and when you edit one: you can't move it to an earlier day. If a past date does get through, saving shows "Holidays can't be set in the past." and nothing is saved — pick today or a later date and click Save again.

A one-off holiday that is already in the past keeps its date. You can still rename it or delete it, and you can move it to today or a later day. Recurring holidays have no date to pick and never add dates before today.

Yes. In the Create Holiday panel, the One-off / Recurring switch changes the fields below it, and the Name you already typed stays. Only the fields for the choice you save with are checked: a one-off needs a Date, a recurring holiday doesn't.

No. You choose One-off or Recurring only when you add a holiday. Editing a holiday later keeps it the kind it is. To change it, click Add holiday to add it the other way, then delete the old one.

Scheduling skips holidays that exist when the schedule is built. A holiday added afterwards — through a preset, a rule, a one-off entry or the monthly extension — can land on a day a lot already has work planned, and nothing moves on its own. The banner counts the lots where that is true — a lot with at least one unfinished task that either has a weekday holiday between its start and due dates that leaves it without enough working days in that span to finish, or starts or ends on a weekday holiday — so you can decide when to move their schedules. A task whose dates were already shorter than its length before the holiday — set that way by hand — isn't counted for a holiday between its dates while it still has a working day; it is only counted if the holiday is its start or due day, or leaves it no working day at all. Click Review and move to see each lot's new projected close before anything changes.

A holiday inside a task's dates only matters when it takes away a working day the task needs, or when it is the task's start date or due date. A task is counted when a weekday holiday falls between its start and due dates and the holiday leaves that span with fewer working days than the task takes, or when its start or due is a weekday holiday. A task laid out with a spare day — say a two-day task scheduled Thursday to Monday, with a new holiday on the Friday — still has two working days to finish in, and the holiday is neither its first nor its last day, so it keeps its dates and its lot is not counted. A task whose dates were already shorter than its length before the holiday — set that way by hand — isn't counted for a holiday between its dates while it still has a working day; it is only counted if the holiday is its start or due day, or leaves it no working day at all. The same rule is why running the move a second time changes nothing: after a task is moved, a holiday can still sit between its start and due dates, but the span has its working days back and no task starts or ends on a weekday holiday.

TPTM works through each lot's unfinished tasks in date order. A task a holiday squeezed gets back its full number of working days, with weekends and holidays skipped, so it finishes later. A squeezed task that starts on a holiday starts on the next working day instead. Every task after it moves out by the same number of working days, even when there are idle days in between. If a later task is squeezed by another holiday, it gets its full length back too, so the lot moves by both. Back-to-back holidays, such as Thanksgiving and the day after, give a task back both days.

A task that already has all its working days but starts or ends on a weekday holiday is taken off it: its start moves to the next working day and its due back to the last working day before the holiday. It keeps the same number of working days, so nothing after it moves because of it.

Tasks running side by side don't add up. When several trades in the same window are each pushed out, the work after them moves by the most any one of them moved, not the total. A task with spare days in its dates absorbs a holiday that falls between its start and due, and doesn't move.

Lots that depend on a moved lot move with it, as listed in the preview. Completed tasks, archived tasks and archived lots are never touched. No work starts earlier. A due that sat on a weekday holiday moves back to the working day before it, so a lot's projected close can land a day or more earlier. Each moved lot's Lot Activity timeline records the move with a note naming the holidays, so nobody has to explain the change afterwards. Running the move a second time changes nothing, because no task is still squeezed by a holiday and none starts or ends on a weekday holiday.

Because it depends on a lot that is moving. When one lot is set up to follow another, moving the first lot off a holiday also moves the lots that follow it — directly or through other lots, including lots that are only moving because they follow — so they stay in step. In the Review and move preview, these lots have a grey line under their name, such as Follows Lot 12, naming the lot that pushed it furthest. That is usually the lot directly before it: in a chain where Lot 13 follows Lot 12 and Lot 12 follows Lot 11, Lot 13's line says Follows Lot 12. When two lots push it the same amount, the one directly before it is named. A lot further up the chain is named only when it pushed further. The summary line counts them, for example "5 schedules (2 follow lots they depend on)". The banner counts only lots that have work on a holiday themselves, so the preview can list more lots than the banner.

A following lot moves only its unfinished work that starts on or after the first holiday that set the chain moving — the holiday the lot at the front of the chain moved off, even when the lot it follows is only following another lot itself. Earlier work, completed tasks and archived tasks keep their dates. A lot with no such work isn't listed and doesn't move, but the lots that follow it still move. Archived lots never move, and neither does a lot that depends on the moving lot only through an archived lot. Each following lot's Lot Activity timeline gets a note such as "Schedule moved 1 working day to follow Lot 12 (Oak Ridge), which moved off Thanksgiving (Nov 26, 2026)."

By the largest move among the lots it depends on, not the total. If a lot follows one lot that moves 1 working day and another that moves 2, it moves 2, and its Follows line names the lot that moved 2.

Both are worked out together, in one move. When its own holiday squeezes work that comes after the work the other lot pushed out, the two add up. For example, a lot that follows a lot moving 2 working days, and also has a task across Christmas Day, moves 3. When both moves come from the same holiday, they overlap instead, and the lot moves by the larger of the two.

Its timeline note says it moved to keep work off its holiday "and to follow" the other lot, and its row in the preview has a Follows line. If its own holidays already move its work as far as the other lot would, it moves only its own amount and has no Follows line.

No. Moving schedules off a holiday always moves the lots that depend on them, so there is no switch to turn this off. This is different from moving one lot's schedule by hand, where you choose whether to Also shift downstream lots — see Adjusting schedule. Only lots that follow a moving lot move with it; the lots it follows stay where they are.

Moving schedules off a holiday only moves work the holiday actually squeezed, or work that starts or ends on a weekday holiday. A task is moved when the holiday takes away a working day it needs, or when the holiday is its start date or due date. When the holiday falls between its start and due, two kinds of task keep their dates:

  • A task that already had a spare day around the holiday, so it still has enough working days to finish.

  • A task whose dates were already too short for its length before the holiday — for example a 7-day task dated Thursday to the following Wednesday, which holds only 5 weekdays. Someone shortened it on purpose, so the holiday doesn't make it move, and it doesn't put its lot in the banner on its own.

A shortened task is never stretched to its full length. If earlier work on the lot moves, it moves later with that work and keeps the working days it had, as far as they fit — when holidays crowd into its new dates it can end up with fewer, never more. Change its dates yourself if it needs more time.

Completed and archived tasks never move either. A task whose due date is earlier than its start date is never taken off a holiday; it moves only when earlier work on the lot moves.

Because its start date or due date was on a weekday holiday. Moving schedules off holidays takes those dates off the holiday even when the task isn't short of working days. Its start moves to the next working day and its due moves back to the last working day before the holiday, so it keeps the same number of working days and stays inside its original dates. For example, with Thanksgiving on Thursday, November 26, 2026, a 1-day task dated Wednesday, November 25 to Thursday, November 26 becomes Wednesday, November 25 to Wednesday, November 25.

Nothing after it moves, and lots that depend on its lot don't move because of it. A start or due on a Saturday or Sunday isn't moved on its own. Completed tasks keep their dates. A task whose due date is earlier than its start date is never moved off a holiday on its own, but it can move when earlier work on the lot moves.

Because the lot's last task was due on a weekday holiday. Moving schedules off holidays moves that due back to the last working day before the holiday — the last day work actually happens — so the projected close lands a day or more earlier. For example, a lot whose last task was due on Thanksgiving, Thursday, November 26, 2026, now closes on Wednesday, November 25. No work starts earlier, and that task keeps the same number of working days.

In the Review and move preview, a lot whose tasks only came off a holiday at their start or end shows Shift (days) 0, with the earlier date under New close. If the earlier close falls in the previous calendar quarter — for example a last task due on New Year's Day, Friday, January 1, 2027, that now ends on Thursday, December 31, 2026 — the row is tagged previous quarter. After the move, the lot's Lot Activity timeline gets a note such as "Schedule adjusted to keep work off Thanksgiving (Nov 26, 2026)."

Because its unfinished work still moved. A completed task can hold the lot's latest due date, so the projected close stays put while the work before it moves out. Every lot the move changes gets an entry on its Lot Activity timeline with the note explaining why, even when its projected close is the same as before. In the preview, such a lot shows the same Current close and New close, and Shift (days) shows how far its remaining work moved — 0 when its tasks only came off a holiday at their start or end, with a note such as "Schedule adjusted to keep work off Thanksgiving (Nov 26, 2026)." A lot whose schedule hasn't started yet doesn't get a new entry; its existing schedule entry is updated instead.

The tag beside a lot's New close means its projected close date moves into a different calendar quarter. Most moves push a close later, so the tag reads next quarter — for example from September 29 to October 1. A close moves earlier only when the lot's last task was due on a weekday holiday and its due moves back to the working day before it. If that crosses into the previous quarter — a last task due on New Year's Day, Friday, January 1, 2027, now ending on Thursday, December 31, 2026 — the tag reads previous quarter. The summary line counts both kinds, for example "(1 leaves its quarter)", so you can see at a glance how many closes shift quarters before you confirm. Quarters are calendar quarters: January–March, April–June, July–September and October–December.

No. The move covers every lot that has work on a holiday at the moment you confirm, and the banner stays until none do. If you don't want a holiday to move schedules at all, delete it instead — or, for a one-off holiday, change its date. A lot whose work was completed or re-dated after you opened the preview is simply left out of the move.

Not from the Holidays page. The move is an ordinary working-day shift, recorded on each lot's timeline, so you can reverse it lot by lot with Move Schedule — see Adjusting schedule.

No. Weekends are never working days, so a holiday dated on one is just a note in your list: it doesn't shift any schedule and never counts toward the "work scheduled on a holiday" banner. The same applies to a recurring holiday whose weekend choice is Keep on the weekend: its weekend dates show a not observed tag. A one-off holiday shows no tag, even on a weekend.

Your company has no recurring holidays and no one-off holidays yet, so there is nothing to list. The page says "No holidays yet. Select presets to start with the US federal holidays, or add a holiday." Click Select presets to start with the US federal holidays, or Add holiday to add a holiday of your own.

You have holidays, just none on the side of the switch you are looking at. "No upcoming holidays." means nothing is dated today or later — for example, your only holidays are one-off days that have already passed. "No past holidays." means none of your holidays has happened yet. Switch between Upcoming and Past above the list to see the rest.

TPTM couldn't fetch your holiday list, often because of a weak connection. It doesn't mean your holidays are gone. Click Try again. If the list had already loaded and only a refresh failed, you see "We couldn't refresh your holidays. Showing the last loaded list." instead: the list on screen is what was there before, and Try again fetches the latest. The message goes away once loading works again.

Both buttons need the Holiday: Create permission; editing a holiday needs Holiday: Update and deleting one needs Holiday: Delete. Recurring and one-off holidays use the same permissions. Unchecking a preset removes it, so that also needs Holiday: Delete: without it, a save that removes a preset is refused with "You do not have permission to perform this action." and nothing changes — not even the presets you checked. Without them you can still see the list and open any holiday to read it. Ask your administrator if you need access — see Organization Memberships and Permissions.

Two reasons are common. Either no lot currently has unfinished work on a holiday — the banner only appears when the count is above zero — or you don't hold the Lot: Update permission, which is what moving schedules requires. Someone who can read holidays but can't update lots sees the page without the banner.

In a leap year the holiday falls on February 29. In every other year it falls on February 28, and the rule's weekend and bridge choices then apply as usual.