Scheduling Templates
Build reusable schedule templates — an ordered critical path plus sub-path tasks — and use them to schedule a lot or a whole community in one step.
Overview
A schedule template is a reusable plan for building a lot: an ordered list of critical path tasks with their durations and stages, plus sub-path tasks that run in the gaps between them. Instead of adding dozens of tasks by hand on every lot, you build the template once and lay it down on a lot — or across a whole community — in one step. Project managers and builder admins create and maintain templates on the Schedule Templates page.
Create a template from scratch, or duplicate an existing one as a starting point.
Sequence critical path tasks and place sub-path tasks between them.
Set the template's duration, mark pay points, and assign stages.
Schedule a lot from the template, or many lots at once with Batch schedule.
Getting to the Schedule Templates page
Open Schedule in the navigation.
Click Schedule templates.
How to create a template
On the Schedule Templates page, click Create.
Type a Template Name and click Create. The new, empty template opens in the editor.
On the Critical Path tab, click Add. Pick the Task, set its Days, choose a Stage, and confirm. Repeat for each task in build order — drag a row to reorder.
On the Subpath tab, click Add for any task that runs alongside the critical path. Pick the Task, its Days, and the critical path tasks it comes After and Before.
Tick Pay Point on any row that should create a pay point when scheduled.
Click Save Changes.
The Schedule Preview above the tables redraws as you edit, so you can check the shape of the schedule before you save. To rename the template, click the pencil next to its name, type the new name, and click the check mark.
How to duplicate a template
On the Schedule Templates page, open the ⋯ menu on the template and choose Duplicate.
Keep the suggested name (the original name followed by - Copy) or type a new one.
Click Duplicate. The copy opens in the editor with all of the original's tasks; the original is unchanged.
How to archive a template
On the Schedule Templates page, open the ⋯ menu on the template and choose Archive.
Confirm. The template disappears from the list.
How to use a template on a lot
Open Schedule → Overall timeline, right-click a day cell on the lot's row, and choose Schedule from template. (The same option is in the Tools menu on the lot's page.)
Pick the Schedule template and check the Date to start schedule from.
Choose a trade partner for each task that does not have one filled in already. To reuse the partners picked the last time this template was used in this community, click Use previous assignments. If the template has not been used in this community yet, the button is greyed out.
Click Schedule. The tasks are created on the lot with working-day dates, and a message tells you how many were created.
To schedule many lots in one pass, use Schedule → Batch schedule instead: pick a community, add and order the lots, choose the template and start date, preview the dates, and click Schedule.
Frequently Asked Questions
What is the difference between the critical path and the sub-path?
What is the difference between the critical path and the sub-path?
The critical path is the main sequence of the build: each task starts the working day after the previous one ends, and their durations add up to the template's calculated duration. A sub-path task runs alongside the critical path in the window between two critical path tasks — the one it comes After and the one it comes Before. When the lot is scheduled, a sub-path task is stretched to fill that whole window, so its own Days value is the minimum time it needs, not its scheduled length.
What is the difference between Calculated Duration and Duration Override?
What is the difference between Calculated Duration and Duration Override?
Calculated Duration is worked out for you from the critical path — the sum of its working days, plus the weekends those days can span. Duration Override is an optional number you type when the template should be treated as taking longer than the calculation; it cannot be lower than the calculated minimum. The template's duration is the target a lot is measured against in Build Days.
Why is a sub-path row red, or why do I see "Invalid Subpath Configuration" when I save?
Why is a sub-path row red, or why do I see "Invalid Subpath Configuration" when I save?
A sub-path task's After task has to come before its Before task in the critical path order, and they cannot be the same task. This usually happens after you reorder the critical path. Edit the sub-path task and fix its After and Before choices, or reorder the critical path, then save again.
Why can't I delete a critical path task?
Why can't I delete a critical path task?
A sub-path task uses it as its After or Before anchor, so deleting it would leave that sub-path task with nowhere to go. You see a Cannot Delete Task message. Edit or delete the sub-path task first, then delete the critical path task.
Why can't I add a sub-path task?
Why can't I add a sub-path task?
A sub-path task needs two critical path tasks to sit between. Add at least two critical path tasks first, then the Add button on the Subpath tab becomes available.
What does the Pay Point checkbox do?
What does the Pay Point checkbox do?
When a lot is scheduled from the template, the task created from a row marked Pay Point starts life as a pending pay point, ready to be confirmed and paid when the work is done. See Pay Points.
Where do the short task codes on the schedule, like FRM2, come from?
Where do the short task codes on the schedule, like FRM2, come from?
From the Abbreviation on each task template, set in Settings → Task templates. When you schedule a lot from a template — with Schedule from template on the website or in the field app, or with Batch schedule — each new task takes its task template's whole abbreviation, so FRM2 stays FRM2. That code is what the Overall timeline's day cells, the Tasks Report's Abbrev column and your trade partners' Schedule Calendar show. To see how codes are set and what they can contain, read Task Templates.
How do I add or change a task template's abbreviation?
How do I add or change a task template's abbreviation?
Open Settings → Task templates, click the task template, click Edit, type the code in Abbreviation and click Save. The rules for what a code can contain are in Task Templates.
If I change a task template's abbreviation, do tasks already on the schedule change too?
If I change a task template's abbreviation, do tasks already on the schedule change too?
Yes, for the tasks that use that task template's description: when you save the new code in Settings → Task templates, those that still carry the old code, or none, switch to it. Tasks that carry a different code keep their own. The details are in Task Templates.
Why don't my task descriptions start with their code any more?
Why don't my task descriptions start with their code any more?
The codes were moved into their own Abbreviation field, and the code still shows in front of the description wherever a task is named, for example FRM2 - Install 2nd forms. You don't need to do anything. More in Task Templates.
Why won't my template name save?
Why won't my template name save?
A name is required and must be different from every other active template's name (upper and lower case count as the same). It can be up to 255 characters, whether you create or duplicate a template or rename one with the pencil in the editor. Spaces at the start or end are ignored, so a name made only of spaces isn't accepted. When duplicating, the copy also needs a name different from the original. A name used only by an archived template is free to reuse.
Why couldn't I archive a schedule template?
Why couldn't I archive a schedule template?
If the archive can't be completed — for example, the template was already archived in another tab — you'll see an error with the reason, the confirmation stays open, and the template stays in the list. Close the dialog and refresh the page to see the current list, then try again if the template is still there.
Can I get an archived template back?
Can I get an archived template back?
Not from the Schedule Templates page — archiving is one-way there. If you may need a template again, duplicate it before archiving the original.
I archived a task template or stage that a schedule template uses. Can I still edit and save that template?
I archived a task template or stage that a schedule template uses. Can I still edit and save that template?
Yes. Rows that were already using that task template or stage keep it, and you can go on editing and saving the rest of the template as normal. What you cannot do is pick an archived task template or stage for a new row, or switch an existing row over to one — that save fails with Failed to update schedule template. Choose an active task or stage for the row and save again.
I'm archiving a task template or stage — how do I know which schedule templates use it?
I'm archiving a task template or stage — how do I know which schedule templates use it?
When you archive a task template (Settings → Task templates) or a stage (Settings → Stages) that schedule templates still use, the confirmation shows an orange message with how many schedule templates use it and their names (the first ten, then "and N more"). Archiving is still allowed — it is a heads-up, not a block. Rows already using it keep it and can still be saved, but it can no longer be picked for new rows. If you would rather not leave those templates behind, open each one first and choose an active task template or stage for the affected rows. Schedule templates you do not have permission to view are not listed, and if nothing uses the item you see the usual confirmation.
What does the orange warning triangle on a template or row mean?
What does the orange warning triangle on a template or row mean?
It means the template still uses a task template or stage that has been archived. On the Schedule Templates page, a triangle after a template's name tells you to open it. Inside the template, an orange Archived tasks in this template message counts the affected rows, and each affected row shows the same triangle next to its description (archived task template) or its stage (archived stage). The template still saves and can still be used, but nobody is maintaining those tasks any more. To clear a warning, edit the row, choose an active task template or stage, and save — the row's triangle and the count go away as soon as you confirm the change, and the template's triangle on the list disappears once you've saved.
Why can't I see Schedule from template?
Why can't I see Schedule from template?
Scheduling a lot from a template adds tasks to the lot and updates the lot, so the Schedule from template option only appears when your role has all three of these permissions: Use schedule template, Create task and Update lot. If any one is missing, the option is hidden from both the Overall timeline menu and the lot's Tools menu. Creating or editing templates needs the Create schedule template and Update schedule template permissions. Ask your administrator to check your role — see Roles and Permissions.
Why does it say "You don't have permission to schedule this lot." instead of showing the form?
Why does it say "You don't have permission to schedule this lot." instead of showing the form?
Scheduling a lot from a template adds tasks to the lot and updates the lot, so your role needs the Create task and Update lot permissions. You see this message when someone sends you a link that opens Schedule from template but your role is missing one of them. Nothing is scheduled and the lot stays exactly as it was. Ask your administrator to add the missing permissions to your role — see Roles and Permissions.
Why is "Delete existing schedule items" switched off, and why can't I turn it on?
Why is "Delete existing schedule items" switched off, and why can't I turn it on?
Deleting existing schedule items needs the Update task permission. Without it, the switch stays off and you see You don't have permission to delete schedule items beneath it. You can still schedule the lot: the new tasks are added and the lot's existing schedule items are kept as they are. If you need the old tasks replaced, ask your administrator to add Update task to your role — see Roles and Permissions.
Was this helpful?