Adjusting schedule
Shift a lot's schedule when dates change — from a single task, by moving the whole schedule a number of working days, or by re-laying it from a template.
Overview
Once a lot's schedule is laid down, real life moves it: a task runs long, weather stops work, or a change order pushes everything out. TPTM gives project managers and schedulers three ways to adjust a schedule without re-entering every task.
From a task — change a schedule task's due date and choose how much of the change overlaps the next tasks and how much pushes them out.
Move schedule — shift every remaining task on the lot forward or back by a number of working days from the Overall timeline.
Schedule from template — replace the remaining schedule with a fresh one from a template, starting on a new date.
How to adjust the schedule from a task
Open a schedule task on the lot — from the lot's page, or by right-clicking its day cell on the Overall timeline and choosing View task.
Change the task's due date. An Adjust schedule section appears saying how many days later or earlier the task now finishes.
Split those days between Overlap (days) and Push out (days) (or Pull forward (days) when the task finishes earlier). The two always add up to the size of the change.
If other lots depend on this one, choose whether to Also shift downstream lots by the same amount.
Save the task. The following tasks move by the push-out amount.
Conceptual video
Learn the basics of this tool and how the different strategies affect the schedule.
Demo
See the tool in action as each strategy is demonstrated from the schedule view.
How to move a whole schedule from the timeline
Open Schedule in the navigation and click Overall timeline.
Right-click the day cell on the lot's row for the date you want the move to start from, and choose Move schedule.
In Move Schedule for the lot, enter Days to move — a positive number pushes the schedule out, a negative number pulls it in. The dialog previews the direction and the date the new schedule will start from, counted in working days — for example, moving 1 day from a Friday previews the following Monday.
If other lots depend on this one, choose whether to Also shift downstream lots by the same amount.
Click Move Schedule. Every incomplete schedule task that starts on or after that date moves by that many working days, and the timeline refreshes.
How to re-lay the schedule from a template
On the Overall timeline, right-click the day cell on the lot's row where the new schedule should start, and choose Schedule from template.
Pick the Schedule template. Leave Delete existing schedule items on so the old tasks from that date onward are archived and replaced.
To keep the work already done and restart part-way through the template, pick a Start from task.
Confirm the trade partners and click Schedule.
Full details are in Scheduling Templates.
Frequently Asked Questions
What is the difference between Overlap and Push out?
What is the difference between Overlap and Push out?
When a task's due date moves later, the extra days have to go somewhere. Push out days move every following task on the lot later by that amount. Overlap days are absorbed instead: the task now runs over the top of the tasks after it, which stay where they are. Set all the days to push out to keep the sequence intact, all to overlap to protect the end date, or split them for something in between. When the task finishes earlier, Pull forward works the same way in the other direction.
Does moving a schedule count weekends and holidays?
Does moving a schedule count weekends and holidays?
No. Days are working days: weekends and your company's holidays are skipped, so moving a schedule 3 days from a Thursday lands the tasks on the following Tuesday.
Which tasks move when I use Move schedule?
Which tasks move when I use Move schedule?
Only the lot's incomplete schedule tasks that start on or after the date you right-clicked. Completed tasks, archived tasks, and tasks that started before that date keep their dates, so history is never rewritten.
Can I undo a move?
Can I undo a move?
There is no undo button. To reverse a move, run Move schedule again from the same date with the opposite number of days — for example, -3 after a move of 3.
Why does it say "Days must not be zero"?
Why does it say "Days must not be zero"?
A move of 0 days would change nothing, so the dialog will not submit it. Enter a positive number to push the schedule out or a negative number to pull it in.
What does "Also shift downstream lots" do?
What does "Also shift downstream lots" do?
Some lots are set up to depend on another lot's schedule. When you push out a lot that others depend on, this switch moves every lot whose schedule depends on it — directly or through other lots — by the same number of days. Archived lots are skipped and their dates stay as they are. A lot that depends on this one only through an archived lot is skipped too, and none of the skipped lots are counted in the number of downstream lots shown. Leave it off to move only the lot you are on.
Why can't I turn on "Delete existing schedule items" when I re-lay a schedule from a template?
Why can't I turn on "Delete existing schedule items" when I re-lay a schedule from a template?
Replacing the old tasks needs the Update task permission. Without it, the switch stays off and shows You don't have permission to delete schedule items. You can still click Schedule, but the new tasks are added alongside the lot's existing ones rather than replacing them. Ask your administrator if you need this access — see Roles and Permissions.
Why don't I see Schedule from template when I right-click the timeline?
Why don't I see Schedule from template when I right-click the timeline?
The option only appears when your role has the Use schedule template, Create task and Update lot permissions. If any one is missing, it is hidden. Ask your administrator to check your role.
Can I move several lots at once?
Can I move several lots at once?
Move schedule works on one lot at a time, plus its dependent lots if you choose to shift them. To schedule a whole community from scratch with staggered start dates, use Schedule → Batch schedule.